Time and Work: LCM Method, Pipes and Cisterns, Solved Examples

Time and work questions ask how long a job takes when people or machines work at different speeds, alone or together. They appear in almost every aptitude test because they check whether you can turn a word problem into rates. Once you think of work as units per day, nearly every question becomes simple addition and division. Pipes and cisterns are the same idea, with emptying pipes counted as negative work.

Asked in: GAT, HAT, NTS, ISSB, PPSC, FPSC, SSC CGL, IBPS PO, CAT

Work as a rate

If a person can finish a job in n days, he completes 1/n of the job each day. This daily share is his rate, or efficiency.

Rates add when people work together. Times never add. If A finishes in 10 days and B in 15 days, together they do 1/10 + 1/15 = 1/6 of the job per day, so they need 6 days, not 25.

The LCM (total units) method

Fractions slow you down. Instead, assume the total work is the LCM of all the given times. Then every rate becomes a whole number of units per day.

Example: times 12 and 18 days. Take work = 36 units, so the rates are 3 and 2 units a day. Every later step (together, alternate days, someone leaving) is just whole-number arithmetic.

Efficiency and comparing workers

Efficiency is the same thing as rate. If A is twice as efficient as B, A does 2 units for every 1 unit of B, and A takes half of B's time.

If A is 50% more efficient than B, their rates are in the ratio 3 : 2 and their times are in the ratio 2 : 3. Time and efficiency are always inversely proportional.

Man-days and the chain formula

When a group of workers does a job, the total effort is workers × days × hours per day. The same job always needs the same total effort.

If the amount of work also changes, divide by the work. This single formula handles almost every men, days and hours question.

Wages and sharing payment

When people are paid jointly for a job, the money is divided in the ratio of the work each one actually did, not the ratio of their days.

If everyone works the same number of days, the work done is in the ratio of their rates, so the wages are also in the ratio of their rates.

Pipes and cisterns

A pipe that fills a tank in n hours adds 1/n of the tank per hour. A pipe or leak that empties a full tank in m hours removes 1/m per hour, so treat it as negative work.

Use the LCM method on the capacity: take the tank as the LCM of all the times, give filling pipes positive rates and emptying pipes negative rates, then add.

Solved examples

  1. Ali can finish a project in 12 days and Ravi can finish it in 18 days. Working together, in how many days will they finish it?
    1. Take total work = LCM(12, 18) = 36 units.
    2. Ali does 36 ÷ 12 = 3 units a day; Ravi does 36 ÷ 18 = 2 units a day.
    3. Together they do 3 + 2 = 5 units a day.
    4. Time = 36 ÷ 5 = 7.2 days, i.e. 7 1/5 days.
    Answer: 7 1/5 days (7.2 days)
  2. Hamza and Neha together can paint a house in 10 days. Hamza alone can paint it in 15 days. How long will Neha take alone?
    1. Take total work = LCM(10, 15) = 30 units.
    2. Together: 30 ÷ 10 = 3 units a day. Hamza alone: 30 ÷ 15 = 2 units a day.
    3. So Neha does 3 − 2 = 1 unit a day.
    4. Neha alone needs 30 ÷ 1 = 30 days.
    Answer: 30 days
  3. 20 workers, working 6 hours a day, build a wall in 15 days. How many days will 18 workers take to build the same wall if they work 8 hours a day?
    1. Use M1 × D1 × H1 = M2 × D2 × H2 because the work is the same.
    2. 20 × 15 × 6 = 18 × D2 × 8
    3. 1800 = 144 × D2
    4. D2 = 1800 ÷ 144 = 12.5 days.
    Answer: 12.5 days
  4. Ayesha can do a piece of work in 20 days and Priya in 30 days. They work together for 6 days, then Ayesha leaves. In how many more days will Priya finish the work?
    1. Total work = LCM(20, 30) = 60 units. Ayesha does 3 units a day, Priya 2 units a day.
    2. In 6 days together they finish 6 × (3 + 2) = 30 units.
    3. Remaining work = 60 − 30 = 30 units.
    4. Priya alone needs 30 ÷ 2 = 15 more days (the whole job takes 21 days).
    Answer: 15 more days
  5. Hamza can do a job in 10 days and Neha in 15 days. With the help of Sana they finish it in 5 days and are paid Rs 4500 in total. What is Sana's share if money is divided by work done?
    1. Total work = LCM(10, 15) = 30 units. Hamza does 3 units a day, Neha 2 units a day.
    2. All three finish 30 units in 5 days, i.e. 6 units a day, so Sana does 6 − 3 − 2 = 1 unit a day.
    3. In 5 days the work done is Hamza 15, Neha 10, Sana 5 units, ratio 3 : 2 : 1.
    4. Sana's share = 5/30 × 4500 = Rs 750.
    Answer: Rs 750
  6. Pipe A can fill a tank in 12 hours and pipe B in 15 hours, while pipe C can empty the full tank in 20 hours. All three are opened together and C is closed after 5 hours. How long does it take in total to fill the tank?
    1. Tank capacity = LCM(12, 15, 20) = 60 units. A adds 5, B adds 4, C removes 3 units per hour.
    2. With all three open the net rate is 5 + 4 − 3 = 6 units per hour; in 5 hours they fill 30 units.
    3. Remaining 30 units are filled by A and B at 9 units per hour: 30 ÷ 9 = 3 1/3 hours = 3 hours 20 minutes.
    4. Total time = 5 h + 3 h 20 min = 8 hours 20 minutes.
    Answer: 8 hours 20 minutes

Exam shortcuts

Common mistakes

Practice MCQs

  1. A can finish a job in 8 days and B in 24 days. In how many days can they finish it together?
    A) 6 days
    B) 5 days
    C) 12 days
    D) 16 days
    Answer: A) 6 days — Total work = 24 units. A does 3 and B does 1 unit a day, so together 4 units a day. Time = 24 ÷ 4 = 6 days.
  2. Kamran finishes one-third of a task in 5 days. How long will he take to finish the whole task?
    A) 8 days
    B) 15 days
    C) 10 days
    D) 20 days
    Answer: B) 15 days — One-third takes 5 days, so the full task takes 3 × 5 = 15 days.
  3. A and B together can finish a job in 12 days. B alone takes 20 days. How many days will A take alone?
    A) 8 days
    B) 24 days
    C) 30 days
    D) 32 days
    Answer: C) 30 days — Total work = LCM(12, 20) = 60 units. Together 5 units a day, B 3 units a day, so A does 2 units a day. A alone: 60 ÷ 2 = 30 days.
  4. A pipe can fill a tank in 6 hours. Because of a leak at the bottom, the leak alone can empty the full tank in 12 hours. How long will the pipe take to fill the tank with the leak open?
    A) 4 hours
    B) 9 hours
    C) 18 hours
    D) 12 hours
    Answer: D) 12 hours — Capacity = 12 units. The pipe adds 2 units per hour and the leak removes 1 unit per hour, so the net rate is 1 unit per hour. Time = 12 hours.
  5. 12 workers can complete a road repair in 18 days. How many days will 27 workers take to do the same job?
    A) 6 days
    B) 8 days
    C) 9 days
    D) 12 days
    Answer: B) 8 days — Man-days stay constant: 12 × 18 = 216. Days for 27 workers = 216 ÷ 27 = 8 days.
  6. A is twice as efficient as B. Together they finish a job in 14 days. How long will A take alone?
    A) 21 days
    B) 18 days
    C) 28 days
    D) 42 days
    Answer: A) 21 days — Let B do 1 unit and A 2 units a day. Together 3 units a day for 14 days = 42 units. A alone: 42 ÷ 2 = 21 days. (42 days is B's time.)
  7. A, B and C can do a job alone in 10, 15 and 30 days respectively. How long will they take working together?
    A) 4 days
    B) 6 days
    C) 7 1/2 days
    D) 5 days
    Answer: D) 5 days — Total work = 30 units. Daily work: A 3, B 2, C 1, so together 6 units a day. Time = 30 ÷ 6 = 5 days.
  8. A can do a job in 9 days and B in 12 days. They work on alternate days, with A working on the first day. In how many days will the job be finished?
    A) 10 1/3 days
    B) 10 1/2 days
    C) 10 1/4 days
    D) 11 days
    Answer: C) 10 1/4 days — Total work = 36 units; A does 4 and B does 3 units a day. Every 2 days they finish 7 units, so in 10 days they finish 35 units. On day 11 A needs only 1 more unit, which takes 1/4 of a day. Total = 10 1/4 days.
  9. A can do a job in 6 days and B in 8 days. With the help of C, they complete it in 3 days and receive Rs 3200. How much should C get?
    A) Rs 400
    B) Rs 600
    C) Rs 800
    D) Rs 1200
    Answer: A) Rs 400 — Total work = 24 units; A does 4 and B 3 units a day. All three do 24 ÷ 3 = 8 units a day, so C does 1 unit a day. In 3 days C does 3 of 24 units, so C gets 3/24 × 3200 = Rs 400.
  10. 16 workers working 9 hours a day dig a 360 m trench in 20 days. How many workers are needed to dig a 480 m trench in 16 days working 8 hours a day?
    A) 24
    B) 27
    C) 30
    D) 32
    Answer: C) 30 — Use M1 × D1 × H1 ÷ W1 = M2 × D2 × H2 ÷ W2. 16 × 20 × 9 ÷ 360 = M2 × 16 × 8 ÷ 480, so M2 = (16 × 20 × 9 × 480) ÷ (360 × 16 × 8) = 30 workers.
  11. Two pipes can fill a tank in 20 minutes and 30 minutes respectively. Both are opened together. After how many minutes should the first pipe be closed so that the tank is full in exactly 18 minutes?
    A) 6 minutes
    B) 8 minutes
    C) 10 minutes
    D) 12 minutes
    Answer: B) 8 minutes — Capacity = 60 units; the pipes add 3 and 2 units per minute. The second pipe runs all 18 minutes and adds 36 units. The first must add the other 24 units, which takes 24 ÷ 3 = 8 minutes.
  12. A alone can finish a job in 24 days. A works for 8 days and leaves; B finishes the rest in 20 days. How long would A and B take working together from the start?
    A) 12 days
    B) 13 2/3 days
    C) 14 days
    D) 13 1/3 days
    Answer: D) 13 1/3 days — In 8 days A does 8/24 = 1/3 of the job. B does the remaining 2/3 in 20 days, so B alone needs 30 days. Together: 1/24 + 1/30 = 9/120 of the job per day, so time = 120/9 = 13 1/3 days.
  13. 4 men and 6 women can finish a job in 8 days, while 3 men and 7 women can finish it in 10 days. In how many days will 10 women finish it?
    A) 35 days
    B) 45 days
    C) 40 days
    D) 50 days
    Answer: C) 40 days — Work is equal: 8(4m + 6w) = 10(3m + 7w), so 32m + 48w = 30m + 70w, giving m = 11w. Work = 8 × (44 + 6) = 400 woman-days. 10 women need 400 ÷ 10 = 40 days.
  14. An inlet pipe fills a tank in 4 hours, but because of a leak the tank takes 4 hours 48 minutes to fill. How long will the leak take to empty the full tank?
    A) 24 hours
    B) 18 hours
    C) 20 hours
    D) 30 hours
    Answer: A) 24 hours — 4 h 48 min = 4.8 h = 24/5 h. Leak rate = 1/4 − 5/24 = 6/24 − 5/24 = 1/24 of the tank per hour, so the leak empties it in 24 hours.
  15. A, B and C can do a job alone in 15, 20 and 30 days respectively. A works every day, and B and C help him on every second day (day 2, day 4, and so on). In how many days will the job be finished?
    A) 9 1/2 days
    B) 9 2/3 days
    C) 10 days
    D) 9 4/9 days
    Answer: D) 9 4/9 days — Total work = 60 units; A does 4, B 3, C 2 units a day. A 2-day cycle gives 4 + 9 = 13 units. After 4 cycles (8 days) 52 units are done. Day 9: A alone makes it 56. Day 10: all three work at 9 units a day and need only 4 units, i.e. 4/9 of a day. Total = 9 4/9 days.

Questions

What is the fastest method for time and work questions?

The LCM method. Take the total work as the LCM of the given times, convert each person's time into units per day, and then only whole-number addition and division are needed.

How are pipes and cisterns related to time and work?

They are the same topic. Filling the tank is the job, each inlet pipe is a worker with a positive rate, and each outlet pipe or leak is a worker with a negative rate.

How do I divide wages among workers?

Divide the total payment in the ratio of the work each person actually did. If all of them worked for the same number of days, this is simply the ratio of their daily rates.

Which exams ask time and work questions?

It is a standard topic in GAT, HAT, NTS, ISSB and public service tests in Pakistan, and in SSC CGL, IBPS PO, SBI PO and CAT in India. Expect one to three questions in most quantitative sections.